Clubhouse Extension phase 1
- 26th May - Ordering Materials.
- 1st June - Preparation made for storage of materials - for instance space cleared in the boat house.
- 2nd June - Materials delivered.
- 4th June - Committee Meeting
- 5th June - Meeting for all the voluteers involved in the phase 1 work.
- 9th June - Scaffolding erected during this week.
- 12th June - Last Evening race before start of work.
- Sat 15th June through Sun 22nd JuneWork on extension by the team of voluteers work to include:
- Partial stripping of roof.
- Construction of timber framworks.
- Flat roof constucted.
- Insulate walls.
- Clad walls with plywood.
- All extension walls clad with plastic shiplap.
- Stairwell roof constructed.
- 20th June - 23rd June - Flat roof laid/
Once the initial external construction has been completed the work on completing the interior will commence and will be onoing.
If anyone can spare the time and can swing a hammer then more voluteers are required for this phase of the building. If you would like to help then please get in touch with the club secretary. See the committee page for the Secretaries e-mail address.